General information

  • Initiator of the project: Fund for Regional Development of the Republic of Buryatia
  • Сontact person: Andrey Torgashin
  • Telephone/Fax: +7 301 2 21-11-49, +7 301 2 21-11-50, +7 301 2 21-11-51 
  • E-mail: info@frr-rb.ru

The project "Adrenaline" (The ski resort on mountain Orlinaya)

The site is 10 km from the center of Ulan-Ude. Maximum natural height of the slopes above sea level (at the Baltic coordinate system) reaches 924 m., with a mean of natural inclines suitable for skiing in the 230-220 m and slopes of up to 820 m. Presentation of the Center for development of extreme sports "Adrenaline"

 

The composition of year-round ski resort includes:

- Ski center with 6 slopes, with the track for roller skis, snow tubing / Rodelban;

 - Hotel 3 * (120 seats); cottage complex (14 to 112 seats); guest house 4 * (80 seats), townhouse (4 to 48 seats);

 - Cafe (120 seats);

 - Restaurant (100 seats); Alpine restaurant (120 seats);

 - Entertainment center;

 - Bath spa complex;

 - Youth athletic center; 

- Equestrian Complex;

 - Bike park with the track for maunting-bike;

 - Tennis courts, playgrounds.

The maximum capacity of the complex - 6200 people per day.

 

 

Key indicators:

Ski slopes with a total area of 27.47 ha and length of 6925 m

Ropeways chair type with total length of 784 m

Ropeways towing type with total length of 1358 m

Ropeways unsupported type with total length of 717 m

The area of buildinginfrastructure is 20.6 ha

Estimated number of tourists at a time on the part of the ski resort - 1,500.

 

Maximum capacity of infrastructure facilities of the resort

Service center

1440

Alpine Restaurant

480

Hotel 3 *

120

Restaurant in hotel 3 *

600

Bath spa complex

99

Cottages 14pcs

112

Hotel (guest house) 4 *

80

Restaurant in hotel 4 *

400

Townhouses 4pcs

48

Total:

3379

 

Investments in the creation of transport and engineering infrastructure

Name of facility

 Price, thous. rubles

Highway №1 from cafe to ring №1

23 213,721

Highway №2 from the camp "Zorka" to ring №1

29 584,404

Highway №6 of rings №2 to junction the road №1

13 439,523

External network (electric and canalization)

56 881,477

Integrated transformer substation, 2 pcs (KTP 1, KTP 2)

14 004,171

ITS

7 678,015

Total

144 801,311

 

The total volume of attracted investments

Investment requirements, total (thousand rubles)

2 277 583

Investment in buildings and structures

1 572 043

Investment in lands

70 651

Investments in intangible assets

0

Investments in financial assets

0

Investment in equipment and other assets

634 889

Investments in prepaid expenses

0

Investment in working capital

0

Raising finance

144 801

Special-purpose financing

144 801

Funds from investors construction

2 132 782

 

Performance indicators of the invested capital

Simple payback

7,62 years

Net present value (NPV)

193 558 thousand rubles

Internal rate of return (IRR)

16,4% (nominal - adjusting for inflation)

Rate of return discounted costs (PI)

1,14 times

Modified IRR (MIRR)

15%

The rate of reinvestment of income

14%

The discount rate of investment costs

14%